Case Study

Experience matters: EV charger rollout for a multi-site data centre client

Image
 

Department

Electrical / EV Infrastructure

Project Value

£10,000 - £50,000 per site

Scope of works

  • Complete site surveys across multiple data centre locations to confirm capacity, routes and connection points.
  • Design a consistent, standardised EV charging bay solution for repeatable rollout across the client’s estate.
  • Coordinate and deliver associated civils (trenching, ducting and groundworks) with minimal day-to-day disruption.
  • Install commercial EV charging points and integrate an app-based platform for access, monitoring and electricity reimbursement.
  • Value-engineer each site to balance cost, performance and scalability.

About

A large data centre operator – a long-standing client – wanted to introduce EV charging across its UK sites. The requirement: a solution that could be rolled out consistently, deliver strong value for money, and provide a simple charging experience for users.

Just as importantly, the client needed visibility and control, including the ability to monitor usage and reimburse electricity costs accurately through an app-based platform.

Based on our 15-year relationship with the client, as well as our proven experience delivering complex electrical projects in operational data centres, they turned to us to assist.

Why EV charging matters for multi-site data centre operators

For data centre environments, EV charging is rarely a nice-to-have. It’s part facilities, part employee (and customer) experience, part sustainability reporting. But it only works if it’s implemented properly:

  • Consistency across sites keeps operations simple for users, facilities teams and finance.
  • Smart management (apps, access control and reporting) turns chargers into an operational asset instead of an admin headache.
  • Scalability ensures today’s rollout doesn’t block tomorrow’s demand.

Challenges

Delivering EV charging across a live, multi-site portfolio brought several practical challenges:

  • Standardisation, without forcing a one-size-fits-none approach: The client wanted a uniform look and feel for the charging bays across all sites, but each location had its own constraints around power availability, routes, and civils.
  • Infrastructure limitations and civils complexity: Careful assessment of civils work requirements – trenching, ducting and groundworks – and planning was needed to avoid unnecessary disruption and rework.
  • Control, reporting and reimbursement: The solution needed to support user authentication, real-time monitoring, and accurate reimbursement for electricity usage, without creating extra admin for the client’s teams.

Solutions

Berkeley delivered a structured, repeatable rollout approach, designed to be replicated from site to site while still reflecting local conditions.

Detailed site surveys and feasibility planning

Across multiple locations, we conducted surveys to:

  • Identify optimal connection points
  • Confirm electrical capacity and layout
  • Assess civils requirements (including trenching, ducting and groundworks)
  • Plan works for efficient delivery and clean reinstatement

A consistent charging bay design (with a “portfolio” mindset)

Berkeley developed a standard charging bay solution to create a consistent end-user experience across the client’s estate, helping the client roll out EV charging in a controlled, repeatable way.

Smart, app-based charging management

To meet the client’s operational requirements, our expert team integrated an app-based platform to enable:

  • User access and authentication
  • Real-time monitoring of charging activity
  • Automated reimbursement for electricity usage

This aligns with our broader approach to commercial EV charging, including smart integration with apps and back-office systems.

Value engineering at each site

Costs varied by location (typically £10,000–£50,000 per site), primarily driven by the scale of civils and any infrastructure upgrades required. We value-engineered each installation, leveraging existing assets where possible while ensuring the solution remained safe, compliant and scalable.

During works

Throughout the rollout programme, our engineers focused on safe delivery, clear communication, and practical coordination on-site:

  • Coordinated civils and electrical works to keep the programme efficient and reduce avoidable site impact.
  • Worked collaboratively with site stakeholders to manage access, sequencing and day-to-day site constraints.
  • Maintained a consistent standard of finish and handover so each site delivered the same experience and operational outcomes.

Completion

Berkeley Installations delivered a standardised EV charging rollout across multiple data centre sites for a long-standing client, balancing consistency with site-specific practicality.

The result was a uniform charging bay solution across the portfolio, backed by app-based visibility and reporting to support monitoring and reimbursement. Alongside improved cost control through value engineering, the rollout also supported the client’s sustainability objectives by enabling EV adoption across their estate.

  • Reduce power draw for their cooling plant.
  • Optimise cooling system performance.
  • Safeguard operational reliability across their European data centres estate.